Development applications in Brewarrina Shire Council
We have no rezoning amendments on record for this council yet, but we track its development applications. The figures below are counted directly from the development application register over the last 12 months.
Development applications · last 12 months
Applications lodged in this council in the trailing 12 months, by current status. Counted directly from the development application register.
- Total lodged
- 9
- last 12 months
- Lodged
- 0
- Under assessment
- 2
- Determined
- 7
- Withdrawn
- 0
See all development applications in Brewarrina Shire Council
Decision speed
How quickly this council determines a development application, measured from lodgement to determination across every decided application that carries both dates.
- Median time to decision
- 24 days
- half are decided faster than this
- Average
- 34 days
- a few slow cases pull this up
- Based on
- 15
- determined applications
Planning disputes
13 on recordPlanning and environment court and tribunal matters naming Brewarrina Shire Council, newest first. Each links to the full public judgment.
| Matter | Court | Decided |
|---|---|---|
| Ngurampaa Limited v Brewarrina Shire Council [2015] NSWSC 1553 PRACTICE AND PROCEDURE – application for joinder – whether a third party should be joined as a party to proceedings in the Supreme Court – whether the joinder is necessary to the determination of all matters in dispute – application dismissed | NSWSC | 20 Oct 2015 |
| Ngurampaa Limited v Brewarrina Shire Council & Anor [2014] NSWSC 1022 CIVIL LAW - radical title - native title - removed case to High Court - removed case to Privy Council - costs order | NSWSC | 25 July 2014 |
| Ngurampaa Ltd v Brewarrina Shire Council [2014] NSWSC 524 PROCEDURE - civil - subpoena - set aside; application to - abuse of process - oppressive - no legitimate forensic process | NSWSC | 22 Apr 2014 |
| Brewarrina Shire Council v Beckhaus Civil Pty Ltd & Anor [2006] NSWCA 361 CONTRACTS – building, engineering and related contracts – alleged non-compliance with contract specifications – payment claimed under s 8 of the Building and Construction Industry Security of Payment Act 1999 – whether breach of contract – measure of damages – assessment of expert evidence | NSWCA | 15 Dec 2006 |
| Brewarrina Shire Council v Beckhaus Civil Pty Ltd & 1 Or [2005] NSWCA 248 BUILDING AND CONSTRUCTION - defective or incomplete work - no damage for defective or incomplete work sustained while contract is on foot and contractor is required to complete the work - termination by agreement - can be ab initio or release from future performance only - implied term that the parties' rights are governed by provisions in the contract relating to completion despite the termination of it - failure to meet contractual standard - evidentiary onus on contractor to prove the contrac | NSWCA | 4 Aug 2005 |
| Beckhaus v Brewarrina No 2 [2004] NSWSC 1160 Building and Construction – Liquidated damages – Whether defendant entitled to liquidated damages under the contract in circumstances where plaintiff did not achieve practical completion - Whether leave should be allowed for claim for liquidated damages - Held - Entitlement to liquidated damages will only arise following upon some other facts which lead to a termination of the contract after the present time - Leave to plead any claim for liquidated damages refused - Whether plaintiff entitled t | NSWSC | 7 Dec 2004 |
| Beckhaus v Brewarrina [2004] NSWSC 840 Building and Construction - Contract - Claim for payment under contract to build earthwork levees - Whether payment claim valid - Cross-claim - Whether lump sum contract - Whether amount properly allowable for provisional variations - Whether practical completion achieved - Whether contractual requirements for progess claim met - Whether any breach of contract in respect of construction of levees - Whether Building and Construction Industry Security of Payment Act 1999 (NSW) applies -Misleading | NSWSC | 16 Sept 2004 |
| Grant v Brewarrina Shire Council [No. 3] [2003] NSWLEC 108 Costs :- in class 4 proceedings - nominal damages awarded - usual order as to costs -exception to general rule - offers to settle | NSWLEC | 26 Mar 2003 |
| Grant v Brewarrina Shire Council [No. 2] [2003] NSWLEC 54 Jurisdiction :- ancillary - damages - unlawful demolition of illegal and dilapidated buildings - nominal damages - exemplary damages | NSWLEC | 6 Mar 2003 |
| Brewarrina Shire Council v Beckhaus Civil Pty Ltd [2003] NSWCA 4 CONTRACT - Superintendent's obligation under AS2124 - 1992 to issue a payment certificate is subject to a condition precedent that contractor support payment claims with evidence and information - Requirement of contractor to provide evidence and information constitutes a condition precedent on either of two bases: a non-promissory condition or an obligation imposed on the contractor, which conditions the superintendent's obligation to issue payment certificate - Requirement of contractor to pro | NSWCA | 17 Feb 2003 |
| Grant v Brewarrina Shire Council [2003] NSWLEC 41 Jurisdiction :- Land and Environment Court - breach of planning law - claim for damages - ancillary jurisdiction available to claim damages | NSWLEC | 11 Nov 2002 |
| Beckhaus v Brewarrina Council [2002] NSWSC 960 Contracts - Building, Engineering and related contracts. - Summary | NSWSC | 18 Oct 2002 |
| SIMMONS v SIMMONS BY HER TUTOR THE PROTECTIVE COMMISSIONER OF NEW SOUTH WALES [1994] NSWCA 368 | NSWCA | 14 Nov 1994 |
Discovery signals matched on council name. We link to the public judgment; we do not reproduce its text.
How these numbers are computed
- Development applications are counted directly from the development application register over the trailing 12 months, grouped by their current canonical status. The full list is on the applications page.