How long does rezoning take in Bogan Shire Council?
Every figure below is computed from the official register records for this council. Counts and gazettal years come from full register history; pipeline duration only from what we have directly observed.
- Amendments tracked
- 1
- full register history
- Active last 12 months
- 0
- by latest status date
- Approval rate
- —
- no outcomes recorded yet
- Observed pipeline duration
- —
- insufficient data yet (0 of 5 cases observed)
Development applications · last 12 months
Applications lodged in this council in the trailing 12 months, by current status. Counted directly from the development application register.
- Total lodged
- 29
- last 12 months
- Lodged
- 0
- Under assessment
- 2
- Determined
- 27
- Withdrawn
- 0
Decision speed
How quickly this council determines a development application, measured from lodgement to determination across every decided application that carries both dates.
- Median time to decision
- 43 days
- half are decided faster than this
- Average
- 53 days
- a few slow cases pull this up
- Based on
- 63
- determined applications
Recent amendments
| Amendment | Stage | Status date | Gazettal | Outcome |
|---|---|---|---|---|
| (NOT PROCEEDING) Bogan Local Environmental Plan 2011 - proposed changes to minimum lot sizes (60 lots) (NOT PROCEEDING) | Withdrawn | 28 Nov 2020 | · | · |
How these numbers are computed
- Volume and gazettals per year count register records directly, full history from the source register.
- Approval rate is recorded outcomes beginning “Approved” over all recorded outcomes. Cases still in flight have no outcome and are excluded.
- Observed pipeline duration is the median days between our first and last stage observation for cases we watched move into approved/gazetted: an observed duration accruing since 12 June 2026, not lodgement-to-gazettal elapsed time, which the registers' list data cannot support. Medians are suppressed below 5 observed cases rather than reported on thin samples.
- Development applications are counted directly from the development application register over the trailing 12 months, grouped by their current canonical status. The full list is on the applications page.