Amendment C074 (South Gippsland)
WatchStage 1 of the realignment of the South Gippsland Highway between Korumburra and Leongatha. The amendment rezones various parcels of land to Road Zone 1, applies a Public Acquisition Overlay and exempts the requirement for a planning permit for native vegetation at clause 52.17.
- Status date
- 31 Aug 2022
- Exhibition
- ·
- Gazettal
- 31 Aug 2022
- Outcome
- Approved
South Gippsland
Council profile →- Amendments tracked
- 109
- Last 12 months
- 4
- Approval rate
- 97%
Stage history
-
Approved / gazetted
source label: “Finished:Approved”
Status date 31 Aug 2022 · Observed 12 June 2026 → current
More in SOUTH GIPPSLAND
- Amendment C133sgip (South Gippsland) Approved / gazetted· 7 May 2026
- Amendment C131sgip (South Gippsland) Approved / gazetted· 4 Mar 2026
- Amendment C132sgip (South Gippsland) Approved / gazetted· 13 Aug 2025
- Amendment C134sgip (South Gippsland) Approved / gazetted· 18 June 2025
- Amendment C129sgip (South Gippsland) Approved / gazetted· 19 Feb 2025
- Amendment C119sgip (South Gippsland) Approved / gazetted· 13 Nov 2024
Planning disputes in South Gippsland
Tribunal and court decisions naming this council, newest first. A signal of contested development in the area, not legal advice.
- Attenborough v South Gippsland SC [2025] VCAT 776 VCAT· 1 Sept 2025· Attenborough v South Gippsland SC [2025] VCAT 776
- Schuhmann v South Gippsland SC [2025] VCAT 676 VCAT· 30 July 2025· Schuhmann v South Gippsland SC [2025] VCAT 676
- Vitetta v South Gippsland SC [2025] VCAT 583 VCAT· 2 July 2025· Vitetta v South Gippsland SC [2025] VCAT 583
- Houben v South Gippsland SC [2024] VCAT 1219 VCAT· 20 Dec 2024· Houben v South Gippsland SC [2024] VCAT 1219
- Prom Country Developments Pty Ltd v South Gippsland SC [2024] VCAT 1015 VCAT· 23 Oct 2024· Prom Country Developments Pty Ltd v South Gippsland SC [2024] VCAT 1015
- Giardino v South Gippsland SC [2024] VCAT 818 VCAT· 28 Aug 2024· Giardino v South Gippsland SC [2024] VCAT 818